A Wendover resident writes:
I visited the HS2 roadshow in Wendover on Saturday 14th May 2011. I went with questions that I had prepared pertinent to each of the consultation questions, and sought out the correct people for the answers. Here’s a summary of my experience… First though, I would like to note that the response from the HS2 representatives was (mostly!) courteous and respectful. I had heard a lot of reports about the members of staff on duty not being able to supply answers. I think it would be fair to say that there was a representative qualified to answer questions on their own specialist subject. If you were able to find that person, then I found that answers were forthcoming (whether or not the answers were correct or appropriate would be for the questioner to decide!). I came away with the very strong understanding that the proposed new railway has absolutely nothing to do with anything other than capacity. This was re-enforced several times by different representatives. Capacity is the driver, not speed, and not connectivity. I now believe that the only way to challenge the proposed railway is to demonstrate that the extra capacity is probably not required, and even if it is, it can be met in other ways. The fact that the business case is dubious, the time savings marginal, and the route destructive will have I believe little bearing on the decision making process. It is now also my view that supporters of the project in Manchester and Leeds (etc) should not be so confident that HS2 will ever reach them. The over-riding purpose of HS2 is to create extra capacity between London and the West Coast Mainline just north of Birmingham.
My Questions:
Question 7: Blight and Compensation.
I spoke to John Sayer of CB Richard Ellis.
CB Richard Ellis are consultants contracted by HS2 Ltd to advise on property-related compensation. I asked John what compensation I would get. We live on Perry Street in Wendover. He told me that we would not be able to make a claim until one year after the railway had been completed and opened. On the current timeline, that’s 2026. At that time, we would be assessed, and compensation *may* become payable. It would be a cash payment, not being linked to a sale of a property.
I asked John if we would be entitled to any compensation in respect of the construction works. He told me that would be very unlikely. He said that the law does provide for such compensation – “Section 10″ – but that he had never known of a successful claim.
John told me that CB Richard Ellis have been contracted to begin work in the New Year (January 2012) on revisions to the compensation scheme as applicable to HS2. I was lead to understand that the responses to the consultation would feed into that work. Assuming of course the project goes ahead.
———————-
Question 2: Value for Money.
I spoke to Stephen McFarlane of HS2 Ltd.
I asked Stephen what the cost of HS2 would be. He told me that “Phase 1″ would cost £17billion, and that “Phase 2″ would cost a further £15billion – totalling £32billion. “Phase 1″ includes London Euston to Birmingham Curzon Street, and the link to HS1. “Phase 2″ includes connections to Heathrow, Manchester and Leeds.
I asked Stephen if the link to HS1 would be open on “Day 1″ – giving an example route of Birmingham to Paris. He told that yes, Birmingham to Paris trains would be possible on “Day 1″. Stephen was careful to note that “possible” means “a path would be available” – and does not necessarily indicate that an operator will be offering those services.
I asked Stephen what the capacity of the HS2/HS1 link would be. He told me that it would be a single track line, with a capacity of 3 trains per hour in each direction (total 6 trains per hour). Whilst he couldn’t give me an exact speed of the trains on that link, we agreed
that it would be “about 30mph”.
I asked Stephen “What is HS2 for?”. He told me that it was for capacity relief, and to reduce journey times. He also told me that HS2 are projecting that 6million journeys will be transferred from aviation. Stephen cited the oft-quoted 3.5 hours journey-time cut-off (it is said by some that if a journey can be completed by train in under 3.5 hours, then most people will chose the train rather than the plane). I demonstrated to Stephen that a journey from Wendover to Edinburgh, using a completely finished new railway (high speed all the way from London to Edinburgh) would be 5hours 12mins – and would not therefore (using his definition) be more attractive. A similar journey from Wendover to Edinburgh by air takes 3hrs 10mins. A journey using today’s railway from Wendover to Edinburgh takes 6hrs 2mins.
Stephen agreed that the reduced journey times would only be of benefit to some people, but that the real benefit and purpose of the project was to generate improved capacity on the West Coast Mainline.
———————-
Question 4: Principles and Specification.
I spoke to Phil Hall of ARUP.
ARUP have been contracted by HS2 Ltd to design the proposed new railway, in accordance with the specifications of HS2 Ltd.
Phil outlined to me the brief that ARUP were given by HS2 Ltd. Phil told me that ARUP were asked to propose a route between a London terminal, and the West Coast Mainline north of Birmingham. Phil told me that HS2 Ltd specified that the proposed railway should run at 400kph, and that it should follow “existing transport corridors”.
Phil explained some of the design practicalities that resulted from the brief. He told me that for a train to run at 400kph, bends in the track must be limited to a minimum radius of 8200 meters (8.2KM – approximately 5 miles), and gradients limited to a maximum incline of 2.5% (1 in 40). Phil explained that reducing the speed of the trains does relax those constraints, but that the speed would need to be reduced by a fair amount before the relaxed constraints allowed significant route changes. Phil told me that (for example) if the specification of the route was for 300kph trains, then the route would not be much different to that proposed for 400kph trains. If the speed of the trains was reduced to 200kph, then the proposed route may have been different. Phil explained that if (for example) the route followed the existing M40 motorway corridor, then the trains would be able to travel at a maximum of 160kph (approximately 100mph).
I asked Phil why the proposed route appeared to bend towards Wendover. Phil told me that the brief from HS2 Ltd was that the route should follow “existing transport corridors” – in this case the existing Chiltern Line railway. I put it to Phil that HS2 and the Chiltern Line were “very different beasts” – and he agreed.
I asked Phil why the railway could not pass Wendover in a deep bored tunnel. Phil told me that it could – that there was “no engineering reason” why HS2 could not be in a deep bored tunnel in the Wendover area. He went on to tell me that ARUP had proposed such a tunnel, but that HS2 Ltd had rejected it – presumably on the grounds of cost.
Phil and I talked about the proposed closure and re-routing of Ellesborough Road. Phil explained that it had been quite challenging to design the route at that point, because the topographical information available was not sufficient. The only information
currently available is that which is published by the Ordnance Survey – which only has a vertical resolution of between five and ten meters. In order to accurately map the area – with enough detail to allow an accurate specification of the elevation of the railway (and therefore whether or not Ellesborough Road would be closed), it would have been
necessary for ARUP to commission a detailed local topographical survey. Phil explained that ARUP had decided not to commission such a survey, because it would have sent the wrong message – implying that work on the project had already begun.
Phil explained some of the other local topographies that had impacted the design of the railway in the Wendover area. Phil told me that the area around Stoke Mandeville through which HS2 is proposed to pass, is a flood plain. For that reason, particular design criteria apply. That is that the railway cannot run at ground level, in a cutting, or in a so-called “Green Tunnel”. The tracks must either be elevated above the flood plain, or in a deep bored tunnel beneath it. Because of the maximum possible gradient noted above, the elevation of the tracks around Stoke Mandeville directly impacts the elevation of the tracks at Wendover, and at Wendover Dean. More generally, I put it to Phil that HS2 was simply a project to “six-track” the WCML – that is, to add two more fast-tracks from London to the area just North of Birmingham. Phil agreed that this was an accurate description. I asked Phil about other proposals that could deliver the same or similar results, but he declined to comment – reminding me of his brief.
———————-
Question 1: Is there a strong case?
I spoke to Alison Munro, Chief Executive of HS2 Ltd.
I asked Alison what the case for the new railway is, and what benefit it will bring. Alison told me that it was to relieve capacity and crowding, and to create time savings.
I demonstrated to Alison that that a journey from Wendover to Edinburgh, using a completely finished new railway (high speed all the way from London to Edinburgh) would be 5hours 12mins – and would not therefore be likely to be more attractive than a journey by air. A similar journey from Wendover to Edinburgh by air takes 3hrs 10mins. A
journey using today’s railway from Wendover to Edinburgh takes 6hrs 2mins. I put it to Alison that whilst the journey cited was a specific case, it was representative of journeys from many towns and villages roughly 45mins or more from London.
Alison agreed that the faster trains would only translate into meaningfully shorter journey times for some people. Alison noted that for example she lived in South London, and with the new faster trains she would be able to make more “day return” trips to places further North – for example, Edinburgh.
I demonstrated to Alison that the journey time from (eg) Birmingham to (eg) Amsterdam or (eg) Paris would be greater than the oft-quoted cut-off time of three and a half hours – and that therefore such a route might not attract much business away from airlines. I also demonstrated that it is already possible to travel by high speed rail from London to a number of continental destinations – but that very few people do so.
Alison agreed on both counts, but went on to tell me that this was not really relevant to the debate and discussion re: HS2, as HS2 is a domestic project designed to create (relieve) capacity on the West Coast Mainline. Alison told me that in fact, the proposed HS2/HS1 link is part of HS2 phase 1, simply because adding it later would be too difficult and disruptive.
I asked Alison how HS2 would bring economic benefit. Alison explained that the majority of the financial benefit came in the shape of time savings. I put it to Alison that many had challenged HS2′s value of time whilst travelling – that is, that time travelling is wasted. Alison countered that by telling me that HS2 Ltd had similarly zero-valued travelling time in the calculations regarding relieving of crowding that it is said that HS2 will bring – and that the two assumptions effectively cancel each other out. More generally, I put it to Alison that HS2 was a “done deal”. Alison insisted that it was not. I asked Alison under what circumstances would the project be cancelled, but she was unable to tell me. I then put it to Alison that if the consultation was indeed genuine, then HS2 was no more than an idea being put forward – with some proponents, and some objectors – that it was no more likely to happen than not to happen – that it was “50/50″. Alison disagreed, telling me that it was the Government’s opinion that the new railway should be built, and that it should be built on the route as described. Alison told me that there was very much more than a “50/50″ chance of it being built.